We’ve been made aware of a date change in this process. The scaffolding is up, but there’s a slight date change for delivery. See below.
Here are some important dates you need to know:
· DONE Wednesday, January 22 – building scaffolding will go up along the west side of the upper parking lot
· NEW DATE: Tuesday, Feb 4 (was Jan 30)– roofing materials delivered
· SAME START DATE: Feb. 3—pre-work begins and actual roof tear off begins Feb 5
· TARGET COMPLETION: April 3 (weather dependent)
Parking:
· Since all temporary parking spaces have been arranged there will be no change to the effective date of Jan 29 for making that switch. Please do not park in the upper lot after Jan. 29.