COMMUNIQUE—New and improved lighting and ceilings begin!

Contractors will begin the ceiling and lighting replacement on Monday, November 30 starting on the 6th floor. Note that the next floor after the 6th will be the 4th floor (to accommodate one of our residents).


6th floor:

Nov 30: Monday- remove all ceiling tiles

Dec 1, 2, 3: Tuesday - Thursday– paint grids and diffusers

Dec 3, 4 and 7: Thursday, Friday and Monday- install ceiling tiles and lighting


4th Floor:

Dec 8: Tuesday- remove all ceiling tiles

Dec 9, 10, 11: Wednesday- Friday – paint grids and diffusers

Dec 11, 14, 15: Friday, Monday and Tuesday: install ceiling tiles and lighting


5th Floor:

Dec 16: Wednesday - remove all ceiling tiles

Dec 17, 18, 21: Thursday, Friday, Monday – paint grids and diffusers

Dec 21, 22, 23: Monday, Tuesday, Wednesday: install ceiling tiles and lighting


Work on the 3rd and 2nd floor will be slightly different and will start Monday, December 28. More information about this will be sent in a few weeks.


While this work should create minimal dust, the contractors regularly work in fully occupied spaces and will be thoroughly cleaning up as they go.


Additionally, the contractors will all be wearing masks while working in the building, and will be limited to using one padded elevator.